On Progress Work:
Construction of
2 units of 700MT PKAD Tanks & 2 units 7500 MT Storage Tanks
Currently, we're doing the construction of the biodiesel tank involves the use of spun pile foundations, employing the pile-driving method with the HSPD (Hydraulic Static Pile Driver) tool, incorporating 300 pile points with a total weight of 7500 tons.
at PT. Teckno Dua Indonesia, Kabil, Batam Island